Grenfell Tower: Could procurement help reduce the current risk?

Few could fail to be affected by the tragic disaster of Grenfell Tower. Understandably there has been a clamour for a quick response to reduce the risk of a repeat, but I wonder if the potential use of procurement as a speedy risk mitigator is being overlooked.

Attention is being given to having the cladding on something like 600 tower blocks tested and fire inspections carried out.  While that will provide some comfort and be politically expedient it there may be faster ways in providing reassurances to those potentially at risk.

Let's face it for cladding to have been installed there needed to be a specification, a contractor and a completion. Would it not be possible to use make use of that trio for providing a quicker response:

  1. Each landlord checks the specification for cladding to see if, with the benefit of hindsight, it satisfies today's safety requirement; (If landlords don't have the capability then perhaps some central support could be provided to QA the specification);
  2. If the specification is considered 'fit for today's needs' we then ask the contractor for a written undertaking as to whether they fitted the specified cladding. Failure to give that undertaking could be place the contractor on a 'naming and shaming list' and potentially be taken into consideration in the award of future contracts. Health & Safety legislation and Contract Law could be used to address those who feel short in delivering the specification;
  3. If the specification is no longer acceptable then at least we have a short list to progress for further prioritisation;
  4. Where the specification is appropriate and the contractor provides an undertaking that they complied, then you can provide some reassurance to residents and move those site visits further down the queue;
If I am correct, this strategy could provide reassurance in hours rather that weeks. Document analysis and quality assurance is at its core rather than the much slower inspection and testing. Is what I propose over-simplistic or have I missed something?

I'm not suggesting there will not be a need for a comprehensive response of testing, inspections, and review of Building Regulations, but that can happen against a background of the proposed prioritisation

Of course, the finger may well be pointed at construction procurement anyway, for example, poor specifying, poor contract supervision and management are obvious potential vulnerabilities, as will be allegations of fraud and corruption!

Tuesday, 9 February 2016

Have the NAO got it wrong on gifts & hospitality?

I read the National Audit Office report on the 'Investigation into the acceptance of gifts and hospitality' with interest but have to say I am mystified. While the EU and United Nations are against the receiving of gifts within a procurement context, the NAO appear to have come to a view that:
While barring UK officials from accepting gifts and hospitality is an option, it would run the risk of hampering the legitimate activities of the departments and officials, including engaging with stakeholders.
How could the refusal of a gift hamper (excuse the pun) business? I am also mystified at the lack of explicit recommendations.

Hospitality and gifts are only targeted at those who are likely to have influence over a decision, and there should be no 'ifs' or 'buts', they are offered to distort decision-making. Of course, the NAO have referred to avoiding perceived conflicts of interest - sorry perception of hampering business is unavoidable when gifts and hospitality are received in the procurement process.

Let's also remember that any gift or hospitality offered is not free from cost - that cost has to be recouped from somewhere and in all probability is an overhead cost included in all public sector contracts.

So what were the examples of gifts received:
These included: tickets to professional sports and cultural events, sometimes accompanied by a spouse and/or children; bottles of champagne; wine for a team’s Christmas lunch; iPads; Fortnum & Mason hamper, a painting valued at £300.
That list is of course constrained by the fact that the systems for recording gifts are not robust and not adhered to anyway.

I didn't pick up anything which specifically addressed staff involved in procurement, but let's remember that if they are MCIPS/FCIPS the CIPS Code of Conduct applies.

Regardless, I think the NAO have missed a mark on this one, a robust approach to the acceptance of gifts and hospitality is not just about the perception of conflicts of interest, it is about protecting staff from potential allegations of bribery and corruption - it should not only be a risk management issue but a health and safety issue too.

Wednesday, 16 December 2015

Santa's procurement hoverboard hell or heaven?

Forget Santa, this could be another bad news day for the procurement profession, given that Amazon have advised customers they should throwaway hoverboards they have purchased due to safety concerns.

Behind the need for refunds will be a calling to account for those who handled the sourcing of the hoverboards and how so many have failed to meet UK, and I assume EU, safety standards. I can visualise the customer helplines of many large retailers being inundated with calls from customers looking for assurances that their hoverboards meet safety standards. Similar calls have probably already been made by CEO's and Marketing Directors!

In those situations Procurement is vulnerable if not culpable. This is an opportunity and a risk for Procurement.
  1. If Procurement were involved but the hoverboards their organisation have on the market are safe, then they need to 'strike while the iron is hot', and get the CEO seizing the opportunity to market the company as a responsible retailer while others have been seen to fail; 
  2. If Procurement were not involved in the sourcing then the case is made for future involvement and the application of procurement risk management tools, including process improvements;
  3. Sadly, if Procurement were involved and the hoverboards now need to be recalled - I hope they believe in Santa too!